2/27/2020

Work Session 19: Track is complete to the end of roadbed at the quarry; this is 75% of mainline! Backdrop pass-throughs opened up. Track circuit wiring (about 60% of total) is complete from west staging to the middle of the helix. Half the backdrop joints have been sanded. All switch machines over the yard are fully wired. All upper level sidings are wired.