3/1/2020
Work Session 20: All backdrop is installed; all but lower peninsula is spackled, sanded, and painted. Yard "modules" were modified and set in place. Ceiling tiles replaced over peninsula. Risers built for yard. Lower peninsula backdrop has been taped/spackled. Running out of material and need additional switches to complete yard; these were ordered. Gaps on peninsula are finished; awaiting additional feeders and cabling. Subroadbed piece needs installation at passenger station junction and risers needed to yard throat, then minor subroadbed fill-in there. New subroadbed needed in yard "foreground".